Casting Of Girders For Superstructures in Viaduct of Metro
Girder
● Girder is the
superstructure of viaduct on which the rail tracks are laid and train runs.
●
It rests on the piers, one
at each end.
●
Since we have two tracks,
each pier supports four U girders (two on each side)
●
U girder weighs around 140
Tons and is 25 m long.
There are 3 bed in the Casting Yard for both U girders and
pier cap –
• Caging Bed
• Casting Bed
• Curing Bed
Each Bed is Capable of Making four Girders simultaneously in
a row.
Methodology :
1.
Four
Cages are fixed at the Cage Bed.
2.
Cleaning
And Oiling of Mould/Shuttering of Casting bed is done.
3.
Lifting
Of Cage and Shifting to Casting Bed is done.
4.
End
Shutters are fixed.
5.
High
Tensile Stress (HTS) Cable and Pre-tensioning prestressing cables are placed.
6.
Inner
Shutters are fixed.
7.
Pre
tensioning of prestressing steel is done.
8.
Concrete
of Specific grade of Concrete is used in pouring and compacted using needle
vibrators.
9.
Curing
is done.
10.
De-Shuttering
is done when Concrete gains required Strength i.e., after 3-4 days.
11.
Lifting
and Shifting of Girder to Staking Yard.
12.
Finishing
of Girder after 21 Days.
Caging Bed For Reinforcement of U-Girders
Typical Cross-section of the Metro Station
Curing of The Girders with a rigid Support between them
Typical Viaducts for the Metro Construction
Viaduct of U-Girders in Mumbai Metro line 7